P-098 · DEMOLITION · NORTH SHORE

Ryde: 1960s brick veneer to slab-ready in 8 days.

8 DAYSDEMO TO HANDOVER96%WASTE RECYCLED$0VARIATIONS

Project overview

A standard knockdown-rebuild in Ryde that turned out to be less standard: asbestos eaves and fibro under the tiles, plus an unregistered in-ground pool found during the pre-demolition inspection.

The challenge

The owners had a fixed slab date with their project builder, five weeks out. Finding asbestos and an extra structure usually means a variation letter and a blown programme — exactly what they’d been warned about by friends.

Our approach

Our pre-demo inspection caught both issues before contract, so they were priced in — not discovered on day two. Licensed removalists cleared the asbestos in two days while we lodged the pool-decommission paperwork. The house came down day four; the pool shell was broken, drained and backfilled with certified fill by day seven.

The outcome

Site handed over slab-ready on day eight, paperwork stack included: asbestos clearance certificate, pool decommission sign-off, tipping dockets and compaction certificate for the pool void. The builder’s slab date never moved. Total variations: zero.

Planning something similar? This was a demolition job — see what’s included and what it costs.
Demolition services →

Tell us about the job.

Price back within 24 hours — or we’ll tell you straight if it’s not our kind of work.